Plan a house budget by stage, by month and by plot size, starting from TKR's per sq ft figure for Tenkasi. See the construction cost guide for what the rate includes.

Construction budget: ≈ ₹24,00,000 · with contingency: ≈ ₹26,40,000 · uses TKR's starting rate of ₹2,000 per sq ft

StageShare %Amount
Site clearing and foundation≈ ₹3,60,000
Columns, beams and roof slab≈ ₹7,20,000
Wall masonry≈ ₹2,88,000
Plastering≈ ₹1,92,000
Electrical and plumbing≈ ₹2,40,000
Flooring and tiling≈ ₹1,92,000
Doors, windows and grills≈ ₹1,68,000
Painting and finishing≈ ₹2,40,000

Shares are re-balanced to 100%. These stage shares are typical planning figures, not TKR rates; adjust them to your plan.

Where the money goes

Total₹24,00,000
  • Site clearing and foundation: ₹3,60,000 (15.0%)
  • Columns, beams and roof slab: ₹7,20,000 (30.0%)
  • Wall masonry: ₹2,88,000 (12.0%)
  • Plastering: ₹1,92,000 (8.0%)
  • Electrical and plumbing: ₹2,40,000 (10.0%)
  • Flooring and tiling: ₹1,92,000 (8.0%)
  • Doors, windows and grills: ₹1,68,000 (7.0%)
  • Painting and finishing: ₹2,40,000 (10.0%)

Hover, tap or use the keyboard on any slice, bar or label to highlight it. Only priced items are charted.

Monthly cash flow

₹0₹12.5 L₹25 L₹37.5 L₹50 LM1M3M5M7M9M10Month
Hover, tap or use the arrow keys on the chart to read values.
● Cumulative spend● Spend in the month

Cost versus plot area

₹0₹25 L₹50 L₹75 L₹1 Cr5001,0001,5002,0002,5003,000Built-up area (sq ft)
Hover, tap or use the arrow keys on the chart to read values.

The dashed line marks your area. The chart includes your contingency.

This is an approximate planning budget, not a quotation. The starting rate covers standard-quality residential construction; land, approvals, compound wall, sump, interiors and premium finishes are excluded. Actual cost depends on design, soil, finishes and material rates. The cash-flow timing is an even spread within each stage.

Enquire on WhatsApp

How to use the planner

Start with your built-up area and the per sq ft rate (prefilled with TKR's ₹2,000), set how many months the build will take, and adjust the stage shares to match your plan. The cost-versus-area chart shows how the budget grows with plot size.

For the materials inside that budget use the construction material calculator, and for financing the home loan EMI calculator.

More free planning tools

Questions

Common Questions

TKR's starting figure for standard-quality residential construction is from ₹2,000 per sq ft. The final cost depends on design, soil, finishes and material rates.
It covers the RCC frame with TMT steel, walls in solid blocks or chamber bricks with plaster, standard tiled flooring, standard doors, windows and grills, basic electrical and plumbing, and standard painting. Land, approvals, compound wall, gate, sump, septic tank, borewell, interiors and premium finishes are excluded.
It spreads each stage evenly over its share of the build duration, so it is a planning view. Real payments depend on your contractor agreement, material purchases and weather delays.
Most builders keep a margin for design changes, rate changes and delays. The planner defaults to 10% and lets you change it.